The Eratupetta-Wagamon road is a beautiful stretch of highway that winds through the lush greenery of Kerala. It is one of the most scenic routes in the state, offering stunning views of the rolling hills and valleys. The winding roads are lined with trees and shrubs, providing a peaceful atmosphere for travelers to enjoy. Along the way, travelers can also experience traditional villages, temples, and tea plantations. This route is known for its breathtaking views and peaceful atmosphere – making it one of the best routes in Kerala.
The reconstruction of the Eratupetta-Wagamon road has been completed, which will boost tourism development. Travel from Pala and Eratupetta to Wagaman will now be easy.
The Uralungal Labor Contract Society completed the road work contract in a re-tender in four months
In October 2021, 19.9 crore was given administrative approval and in December 2021, technical approval was given for the rehabilitation of the road, which had been dilapidated for more than ten years. BMBC, with financial support from KIFB, planned to build the road to the standard.
In February 2022, a contract was signed for ₹16.87 crore to complete road work within six months. However, the contractor who defaulted on the construction work was dismissed.
Later, the Uralungal Labor Contract Society took the second tender and completed the construction of a 24 km road in four months.